I have a question about the update of field progress on a projet : I have make test to know how update manually or by following a parameter, to update this field, but this field is only updated to only "100%" when I change the status to "done", "verified", "validated", etc.
Could you explain me how does it work to set this field ? I think he is not used only to display "100%" when the project is done, I need to display for sample, "50%" if the projet is in progress.
first one in Progress section displays "real" progress, corresponding to real work.
To have it calculated, you must enter assigned work on activities, then enter real work and possibly update left work
second on is directely entered on the project by project leader
It is just an estimate from the project leader
Values are numeric, but it is just display, you can change it in parameters and have textual values (not started, started, almost finishzd, ...)
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.