Able to input "Planned work allocation" ?

More
25 Jun 2018 14:33 #1 by dnaton
Hello,

I ask me if there is a way to input "planned work" ?

The idea is to have (in french, sorry, I don't know the english term) "un planning estimatif de charge".

With theses inputs, I can have a more precise view of the future charge of my team on the month (or next month)

For the moment, I input in advance real work allocation but it is not a good thing : the reports in Projeqtor considers theses inputs like real work (it's normal :-) ) and my reports are also not right :-(

Is what I ask for possible ? If yes, could you give me some clues ? ;-)

Regards,
Damien
.
ProjeQtOr v11.0.1 - Apache v2.4.56 - MariaDB v10.4.28 - PHP v8.2.4
Plugins installed : Personalized Translation 1.5 - Customization of screen 6.6

Please Log in or Create an account to join the conversation.

More
25 Jun 2018 17:59 - 26 Jun 2018 10:43 #2 by alainforma
it is not possible to do manual planning because, on the one hand, it is useless and cumbersome. Often this type allows work overloaded (sometimes blithely) that we refuse to do. Projeqtor has many planning modes that meet most needs while respecting the real capacity and availability of your resources.
Last edit: 26 Jun 2018 10:43 by babynus.

Please Log in or Create an account to join the conversation.

More
08 Jun 2019 16:54 #3 by al_rodin
Hello,
I wake up this message because I found other answers about this in your Blog and I don't want to launch a new thread.
I absolutely agree with you, but let me please only justify this request which also comes from me.
When you calculate Earned Value for a Project (which is the first KPI), you need:
Planned work PV at a certain date, in measure units (days, hrs or whatever)
Actual costs AC in the same date , in money (not the real work, the real costs. It's different)
Real work done, in the same date.(in the same unit of measure than PV)
In Projeqtor you can get the last two. You instead can't get how many time a resource should have had to consume at that date (the planned work). The Gantt only shows the time within the resource should be employed, not a specific charge of hrs per each day. This is in my opinion what the request asks for.
Regards
Lorenzo

Please Log in or Create an account to join the conversation.

More
08 Jun 2019 20:24 #4 by babynus

In Projeqtor you can get the last two. You instead can't get how many time a resource should have had to consume at that date (the planned work).

Yes you can.
It is what Baselines stand for.
Try and save project baseline, and few time later use report "S-curve" chart.

Babynus
Administrator of ProjeQtOr web site

Please Log in or Create an account to join the conversation.

More
11 Jun 2019 08:33 #5 by al_rodin
Hello Babynus,
thanks a lot for your info. Very useful!
From the other side now it's clear for me which kind of feature could be also useful. I will open a new thread for this, just to have some hint from you.
Thank again and regards,
Lorenzo

Please Log in or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.054 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.