I've been spending time getting to know this application in order to use it for teaching Project Management at a university. So far so good!
My question is, is it possible to set an activity to be continuous?
Obviously, there will be weekends (and sick days ideally), but can I at least make sure that a resource won't be diverted to another activity halfway through the current activity? I know this is rarely relevant as most tasks can be dropped and picked back up, but I can't stop cooking roast dinner halfway through without it taking longer overall!
For example, I have two tasks that use the same resource (called "Atelier"). One of these tasks is part of the critical path but starts after the earliest start date of the other one. The result is as below. What I would like is for one of the tasks to be delayed such that neither is interrupted by the other.
You can use either - the planning mode " must not start before the validated start date"
or - create a dependency beetween activities with a mode end-start.
There is no planing mode "not interrupted".
Only solution is one proposed by alainforma : add dependency so that second cannond start before first is ended.
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.