14 Mar 2019 16:30 #1 by clarezoe
Invalid controls was created by clarezoe
Hi,

I can't set an activity to "done". I got the error "the field 'result' is mandatory". Where and when should I fill the result?

Thanks!

Please Log in or Create an account to join the conversation.

More
15 Mar 2019 06:57 - 15 Mar 2019 06:57 #2 by Envergus
Replied by Envergus on topic Invalid controls
like this:

The vertical red line shows that it is mandatory just when you select "done"
Attachments:
Last edit: 15 Mar 2019 06:57 by Envergus.

Please Log in or Create an account to join the conversation.

More
15 Mar 2019 09:27 #3 by babynus
Replied by babynus on topic Invalid controls
This control is managed through definition of type.
Go to the Activity type, you'll see that there is an option "mandatory result on done status" ...

Babynus
Administrator of ProjeQtOr web site

Please Log in or Create an account to join the conversation.

More
18 Mar 2019 07:37 #4 by clarezoe
Replied by clarezoe on topic Invalid controls
Thanks! I must be blind!!! :blink: :S

You guys are awesome!!

Please Log in or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.041 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.