View ProjeQtOr On SourceForge.net
ProjeQtOr - Project Management Tool
Supportez nous sur Capterra
OIN - Open Invention Network
ProjeQtOr free project management software - [SOLVED] Detailed work per resource - weekly - ProjeQtOr

Prochaines Sessions

Les prochaines formations et démonstrations sont ouvertes, inscrivez-vous rapidement !

 

Démonstration de ProjeQtOr

(gratuit, sur inscription)
 

3 décembre (16h-17h30)

9 janvier 2025 (10h30-12h)

4 février 2025 (16h-17h30)

6 mars 2025 (10h30-12h)

 
 

Planifiez avec ProjeQtOr

19 et 20 novembre (14h-17h30)

21 et 22 janvier 2025 (9h-12h30)

18 et 19 mars 2025 (9h-12h30)

 
 

Administrez avec ProjeQtOr

26 et 27 novembre (14h-17h30)

28 et 29 janvier (9h-12h30)

25 et 26 mars (9h-12h30)

 

 

 

[SOLVED] Detailed work per resource - weekly

More
06 Avr 2024 08:56 #1 by chandrashekhar
Hi,

We are using scheduled report in a mail regarding the subject. Today noticed something unusual in the report when checked via email. I attempted to reproduce the issue but was unsuccessful. However, I wanted to bring it to your attention in case you've received a similar query and have a solution. I've attached a screenshot of the email where the report displays the resource ID instead of the name, although the name appears when checked in the resource. Can you please assist with this?

ProjeQtOr Version: 11.1.5

Thank you.
Attachments:

Please Connexion or Create an account to join the conversation.

More
10 Avr 2024 11:21 #2 by maxca
Hello,

I don't reproduce your problem either. Do you have the same problem looking directly at this report in projeqtor? If so, do you have any log errors? console errors?
You should receive the report tomorrow (right?). Let us know if it continues, we'll keep it in mind.
Thanks you

Maxca

Please Connexion or Create an account to join the conversation.

More
10 Avr 2024 11:42 #3 by chandrashekhar
Hi,

Q. Do you have the same problem looking directly at this report in projeqtor?
A. I don't have the same problem looking directly at this report in projeqtor.

Q. If so, do you have any log errors? console errors?
A. No, If you guide me I can get it.

Q. You should receive the report tomorrow (right?).
A. Report is scheduled on every Saturday at 9:45 (IST)
 

Please Connexion or Create an account to join the conversation.

More
10 Avr 2024 12:11 #4 by maxca
is it a new resource? this week, do you see the resource name correctly?

Please Connexion or Create an account to join the conversation.

More
10 Avr 2024 12:33 - 10 Avr 2024 12:35 #5 by chandrashekhar
Yes, it's a new resource, I have checked name before giving feedback, also checked today too, I can see the resource name correctly.Please find Attached image for reference.
Attachments:
Last edit: 10 Avr 2024 12:35 by chandrashekhar. Reason: additional information

Please Connexion or Create an account to join the conversation.

More
10 Avr 2024 14:25 #6 by maxca
No. I wanted to know if this week's report (15) included the resource name correctly.
Can you tell me whether this resource is: " is a contact, is a user, is an employee, is a student, is outsourced, is manager of leaves, is material resource "

 

Please Connexion or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.043 seconds

Paramétrages de cookies

×

Cookies fonctionnels

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Veuillez vous connecter pour voir vos activités!

Autres cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.