Hello,
i have two questions :
1 / Is it possible on the planning view, to see the "validated planning" instead of the "real planning" ? Like for example :
i would like on the green lines to see the date 06/07-30/07
In fact i'd like to the see the validated planning which is available as soon as there is no imputation on the project. I know one way, with the possibility to save a reference, but i'd like to know if it's possible if there are imputations on the project and the manager didn't make a reference.
2/ I've tried to adapt some parameters like mentionned
here
, so now i don't have "read only" in /var/www/html/projeqtor/model/PlanningElement.php :
"plannedStartDate"=>"noImport",
"plannedEndDate"=>"noImport",
"plannedDuration"=>"noImport",
"realStartDate"=>"noImport",
"realEndDate"=>"noImport",
"realDuration"=>"noImport",
but it doesn't change anything. Do i have to restart some services ?
Thank you