ProjeQtOr free project management software - [SOLVED] How can I mark future work days in planning? - ProjeQtOr

Prochaines Sessions

Les prochaines formations et démonstrations sont ouvertes, inscrivez-vous rapidement !

 

Démonstration de ProjeQtOr

(gratuit, sur inscription)
 

13 mai 2025 (10h30-12h)

5 juin 2025 (16h-17h30)

 
 

Planifiez avec ProjeQtOr

14 et 15 mai 2025 (9h-12h30)

18 et 19 juin 2025 (9h-12h30)

 
 

Administrez avec ProjeQtOr

20 et 21 mai (9h-12h30)

25 et 26 juin (9h-12h30)

 

 

 

[SOLVED] How can I mark future work days in planning?

More
04 Fév 2021 11:45 #1 by DaniSLB20
Is it possible to, lets say, a certain person will be occupy in the 5 next days with projet X activity Xx how can I mark on the planning that?
I need specific help on this as I'm not able to find anything like that.

Please Connexion or Create an account to join the conversation.

More
04 Fév 2021 15:00 #2 by Arkhanje
It seems to me that you should read the manual carefully, especially the parts: graphical user interface, common section and planning which will allow you to have the basics of ProjeQtOr for the creation of your planning.

Otherwise to answer your question:

You create your project
You allocate your resources to the project
You create your activity in your project
You assign the resource to the activity
You assign 5 work days to this resource.

Activities are created in the "as soon as possible" mode, so immediately. You then have several options to block this activity at a later date:

- Use a fixed milestone - fill in the milestone date and link the activity to this milestone with an end-start dependency. The activity will then be placed at the level of this milestone
or
- use the planning mode "does not start before the validated date" on this activity in the Progress> management section and enter the date on which the activity must start.



I hope that answers your question.
Good continuation

Please Connexion or Create an account to join the conversation.

More
04 Fév 2021 15:07 #3 by DaniSLB20
Sorry I don't think I explained myself well.

Let's imagine that the resource is already alocated to the project and activity, now what I'm trying to do is the resource x will be occopied on the 05/02/2021, 08/02/2021, 09/02/2021 (future days), and on reports-planning-Colored monthly resource planning, the calendar of the resouce x will have the grey square planned market for future work.

Please Connexion or Create an account to join the conversation.

More
05 Fév 2021 21:35 #4 by babynus
Use screen Absence, and chech days when resource is "occupied"

Babynus
Administrator of ProjeQtOr web site

Please Connexion or Create an account to join the conversation.

More
10 Fév 2021 16:41 #5 by DaniSLB20
Our company updated the projeQtor version to 9.04 now I've got the option to mark future work, but when I go to planend interventions it shows the following:

"To display selectable activities, define activities in 'manual' planning mode" What do I have to do in order to show the activities for me to select?

Please Connexion or Create an account to join the conversation.

More
10 Fév 2021 16:47 #6 by babynus

"To display selectable activities, define activities in 'manual' planning mode" What do I have to do in order to show the activities for me to select?

Do exactly whet is explained in the message : select the activity you want to plan manually, and change its planning mode to "manual planning" (then save)

Babynus
Administrator of ProjeQtOr web site

Please Connexion or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.049 seconds

Paramétrages de cookies

×

Cookies fonctionnels

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Veuillez vous connecter pour voir vos activités!

Autres cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.