View ProjeQtOr On SourceForge.net
ProjeQtOr - Project Management Tool
Supportez nous sur Capterra
OIN - Open Invention Network
ProjeQtOr free project management software - change activities status - Page 2 - ProjeQtOr

Prochaines Sessions

Les prochaines formations et démonstrations sont ouvertes, inscrivez-vous rapidement !

 

Démonstration de ProjeQtOr

(gratuit, sur inscription)
 

16 juillet (10h30-12h)

22 août (16h-17h30)

12 sept (10h30-12h)

1er oct (16h-17h30)

 
 

Planifiez avec ProjeQtOr

18 et 19 septembre (9h - 12h30)

 
 

Administrez avec ProjeQtOr

25 et 26 septembre (9h - 12h30)

 

 

 

change activities status

More
30 Aoû 2022 13:37 #7 by loicr
Replied by loicr on topic change activities status
So if a subtask is going to terminated, the parent will not go to terminated ? only work for in "inprogress" and "done" ?
I've got trouble for closing project because a lot of upper task are not same status as subtask.
Thanks for clarification.
I see on one post that we can force closing of projet even if task are not finished and closed but i am unable to find how to do that (i've got projectexpense linked termined also.. seems not considered as closed ! ).

Please Connexion or Create an account to join the conversation.

More
30 Aoû 2022 20:02 #8 by babynus
Replied by babynus on topic change activities status

I see on one post that we can force closing of projet even if task are not finished and closed but i am unable to find how to do that

It's in "specific access rights"

Babynus
Administrator of ProjeQtOr web site

Please Connexion or Create an account to join the conversation.

More
31 Aoû 2022 12:14 #9 by loicr
Replied by loicr on topic change activities status
Thanks a lot for closing / Solved !!! :)

But for a task "Phase" with 1 subtask, how could it be possible that if subtask go to terminated the task "phase" is going to terminated ?

LR

Please Connexion or Create an account to join the conversation.

More
31 Aoû 2022 14:15 #10 by babynus
Replied by babynus on topic change activities status
This can be configured in global parameters : automatically change status of parent
This will put parent to first status "in progress" when first child moves to "in progress"
This will put parent to first status "done" when last child moves to "done"

Babynus
Administrator of ProjeQtOr web site

Please Connexion or Create an account to join the conversation.

More
05 Sep 2022 10:05 #11 by loicr
Replied by loicr on topic change activities status
Ok Solved.
Thanks.

LR

Please Connexion or Create an account to join the conversation.

More
05 Sep 2022 14:57 #12 by theoMan5
Replied by theoMan5 on topic change activities status
useful information

Please Connexion or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.056 seconds

Paramétrages de cookies

×

Cookies fonctionnels

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Veuillez vous connecter pour voir vos activités!

Autres cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.