View ProjeQtOr On SourceForge.net
ProjeQtOr - Project Management Tool
Supportez nous sur Capterra
OIN - Open Invention Network
ProjeQtOr free project management software - Cost of a resource - ProjeQtOr

Prochaines sessions de formation

Les prochaines formations et démonstrations sont ouvertes, inscrivez-vous rapidement !

 

Démonstration de ProjeQtOr

(gratuit, sur inscription)

Mardi 23 avril (10h30-12h)

Jeudi 16 mai (16h-17h30)

Jeudi 13 juin (10h30-12h)

 
 

Planifiez avec ProjeQtOr

3 et 4 avril (9h - 12h30)

 
 

Administrez avec ProjeQtOr

10 et 11 avril (9h - 12h30)

 

 

 
 

Cost of a resource

More
22 Fév 2017 18:18 #1 by VERGES
Cost of a resource was created by VERGES
We have assigned a resource of a project with his cost field not filled in.
A real work alocation has been made by this ressource with a cost = 0 €.

Now, the Project Manager has assigned a cost to this ressource. But the economy of the project is false because the old real work allocation was based on a cost=0€.

Do you know if it is possible to make an update fo the project in order ton integrate the cost of the ressource for the old real work allocation??

Thanks,

Pascal

Please Connexion or Create an account to join the conversation.

More
22 Fév 2017 18:59 #2 by VERGES
Replied by VERGES on topic Cost of a resource
A precision on this ticket:
If we change the "start date" of the resource (function and cost field), and the cost , the tool doest not update the cost of the resource in the past.
The margin of the project (project view) is false...

Please Connexion or Create an account to join the conversation.

More
27 Fév 2017 20:30 #3 by babynus
Replied by babynus on topic Cost of a resource

Now, the Project Manager has assigned a cost to this ressource. But the economy of the project is false because the old real work allocation was based on a cost=0€.

I just did the test and it worked well.
I repeted it on demo, and still works well :
Create project "no cost".
Create resource "no cost", with no cost, defaut function "manager".
Allocate resource "no cost" to project "no cost".
Add activity "no cost activity" on rpoject "no cost".
Assign resource "no cost" to "no cost activity" with function manager.
Add one real work day for "no cost" on "no cost activity" in the past (20/02) now (27/02) and in the future (06/03).
Real cost of activity is zero.
Add cost for resource "no cost", function "manager", 100€/day.
Cost for activity is automatically updated to 300€, and so is the project.

Babynus
Administrator of ProjeQtOr web site

Please Connexion or Create an account to join the conversation.

More
28 Fév 2017 15:38 #4 by VERGES
Replied by VERGES on topic Cost of a resource
It was a mistake alocating a bad profile (without cost) to the activity.

Thanks you,

Please Connexion or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.044 seconds

Paramétrages de cookies

×

Cookies fonctionnels

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Veuillez vous connecter pour voir vos activités!

Autres cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.