babynus wrote: It means that resource still has 0,19 d left to do on this meeting,
=> true.
babynus wrote: but possibly it is a passed meeting,
=> true
babynus wrote: and resource azlready entered real work for the corresponding day.
=> I understand that just saving the "pre-real work" means that the real work for the day is entered, even if I set remove the "0" value for the day.
Is that correct?
babynus wrote: He should just set left to zero.
=> I understand that "he" means the ressource. When you put "0" to "left work" , this does not give any information about the "real work" right? not even by adding the "assigned work".
One more thing: I tried to put a "0" in "left", then I realized that "no real work" was counted, so I put a "0,19" in the "real work" for this line, it then set the "reassessed" to "0,19".
So I removed the "0" from the "left work" => reassessed went to "0,38".
I removed the "real work", the "left work", and saved:
I add "0,19" in real work
Now I got the "reassed" to "0,19"
What does this mean? What and where are the impacts?
Kitcat711