View ProjeQtOr On SourceForge.net
ProjeQtOr - Project Management Tool
Supportez nous sur Capterra
OIN - Open Invention Network
ProjeQtOr free project management software - How to enter backdated tasks, and let ProjeQtor re-schedule the project - Page 3 - ProjeQtOr

Prochaines Sessions

Les prochaines formations et démonstrations sont ouvertes, inscrivez-vous rapidement !

 

Démonstration de ProjeQtOr

(gratuit, sur inscription)
 

13 mai 2025 (10h30-12h)

5 juin 2025 (16h-17h30)

 
 

Planifiez avec ProjeQtOr

14 et 15 mai 2025 (9h-12h30)

18 et 19 juin 2025 (9h-12h30)

 
 

Administrez avec ProjeQtOr

20 et 21 mai (9h-12h30)

25 et 26 juin (9h-12h30)

 

 

 

How to enter backdated tasks, and let ProjeQtor re-schedule the project

More
01 Jui 2018 15:54 #13 by alainforma
hi
i am thinking about one thing ! Project under construction does not appear on real work allocation. Please check this box it could be our solution.

Please Connexion or Create an account to join the conversation.

More
04 Jui 2018 07:22 #14 by NarayanAras

alainforma wrote: hi
i am thinking about one thing ! Project under construction does not appear on real work allocation. Please check this box it could be our solution.


In the Projects screen, the lower half of the screen has Treatment section. It shows the following status:
1. The under construction check box is cleared (no tick)
2. The handled check box has a tick in it. But its date was wrong: 4th April 2018. But the project was rescheduled (preponed) to week#5. Therefore I suspected that this could be a reason why the project does not show the tasks in Real work allocation. So I changed this date to 1st Jan 2018. But even now it does not show the planned work for the three resources in week#5 and #6.

Please Connexion or Create an account to join the conversation.

More
04 Jui 2018 12:49 #15 by babynus
You screenshot show that parameter "hide not handled tasks" is not displayed to user.
This means that this feature has been activated globally, on Global Parameter screen.
Then, users see on their Timesheet only activities that are in status handled (or over).
Change status of activities to see them, or disable this paramerter.

Babynus
Administrator of ProjeQtOr web site

Please Connexion or Create an account to join the conversation.

More
04 Jui 2018 13:33 #16 by NarayanAras
Thanks Babynus, for that tip!

Yes, I corrected that global parameter, and now all resources can see the tasks from the Timekeeper (admin-type) project.

To conclude, this is a minor bug: [BUG]

The Administration projects should be exempted from this global parameter, because the tasks in it are always "dummy", and all resources in the organization would be entering time tickets repeatedly against the same tasks.

Thus these admin-type tasks (leave, training...) cannot have any responsible person for them, any start date, any handled status, etc to begin with.

Please Connexion or Create an account to join the conversation.

More
04 Jui 2018 13:36 #17 by babynus

The Administration projects should be exempted from this global parameter, because the tasks in it are always "dummy", and all resources in the organization would be entering time tickets repeatedly against the same tasks.

No, I don't agree at all.
It is not because they are Administrative that they don't have a workflow.
I have "Holidays 2018" that is in progress, in have created "Holidays 2019" but it is still "recorded". It will be "In progress" in september. So I can prepare next Admoin tasks...

Babynus
Administrator of ProjeQtOr web site

Please Connexion or Create an account to join the conversation.

More
04 Jui 2018 13:42 #18 by NarayanAras
Oh ok, I see what you mean: All these tasks won't be handled till the project is actually started off. Yes, that's right!

BTW I had raised BUG#2 on 1st June. I await your response to that.

Thanks in advance!

Please Connexion or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.058 seconds

Paramétrages de cookies

×

Cookies fonctionnels

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Veuillez vous connecter pour voir vos activités!

Autres cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.