Imputations form displays activities, but resource no longer assigned to project

More
18 Jan 2019 19:10 #1 by phvincent
Hello All support team (wishing you a nice 19 year !)

I've got a (non-blocking) issue on imputations forms for my resources: when a resource has an expired affectation to a project, he/she continues to see some activities of this project in his/her timesheet ... but not the project. Thus the resource sees "orphan" activities (although they're really linked to the project).
For example, assuming I have project P1 and activity A1 in this project. 2 human resources R1 et R2 both assigned to A1. Assume R1 has an active affectation to P1 and R2 has an expired affectation to P1. R1 will see a correct timesheet with 2 hierarchical lines:
P1
A1

However R2 will see a time sheet with only A1 => bad

I didn't find similar query on the forum, so let me know if it's a known issue and if a corrective patch is planned. I'm using v7.2.4

Best regards

Please Connexion or Create an account to join the conversation.

More
20 Jan 2019 14:29 #2 by babynus
Hi,

This seem to be a display issue.
Ticket #3787 recorded

Babynus
Administrator of ProjeQtOr web site

Please Connexion or Create an account to join the conversation.

More
28 Jan 2019 12:00 #3 by babynus
Hi,

I cannot reproduce on V7.3.3 (patched to V7.3.4)





Wan you please post screenshots of you situation, with details for :
- allocation of resource to project
- assignment of resource to activity
- display of Timesheet.

Thanks.

Babynus
Administrator of ProjeQtOr web site
Attachments:

Please Connexion or Create an account to join the conversation.

More
02 Fév 2019 18:24 #4 by babynus
I tried again to reproduce your issue, without success.
I tried :
- set end date of allocation in the past => no issue
- close allocation => no issue
- remove alocation => no issue

Can you please try and reproduce on Demo ?

Babynus
Administrator of ProjeQtOr web site

Please Connexion or Create an account to join the conversation.