View ProjeQtOr On SourceForge.net
ProjeQtOr - Project Management Tool
Supportez nous sur Capterra
OIN - Open Invention Network
ProjeQtOr free project management software - How to get planned end date in time sheet to show orginal planned end date - ProjeQtOr

Prochaines sessions de formation

Les prochaines formations et démonstrations sont ouvertes, inscrivez-vous rapidement !

 

Démonstration de ProjeQtOr

(gratuit, sur inscription)

Mardi 23 avril (10h30-12h)

Jeudi 16 mai (16h-17h30)

Jeudi 13 juin (10h30-12h)

 
 

Planifiez avec ProjeQtOr

3 et 4 avril (9h - 12h30)

 
 

Administrez avec ProjeQtOr

10 et 11 avril (9h - 12h30)

 

 

 
 

How to get planned end date in time sheet to show orginal planned end date

More
29 Aoû 2019 16:47 #1 by beverley
The problem we have is we do not know when planning that the assigned work days might be longer than expected. We need to find a way for those completing the time sheets to record the actual time, increase the assigned to time and still show in the time sheet when the activity needs to be completed.

How to get planned end date in time sheet to show orginal planned end date?

What seems to happen is user record in time sheet eg. 1 day used at start of the task. e.g 1st August, where orginally planned start date is 1st Aug to 7th Aug. The action of recording the 1 days (expected time) updates the activities planned start and end date to 1st Aug (with out running planning). The time sheet now shows the activity as planned for 1st Aug to 1st Aug. If the user updates the required assigned days to say 2. The time sheet still shows the planned start and end date as 1st August, so user can not see in time sheet when activity is originally required for (planned end date). Since this happens a lot especially where the project manager has little idea of work time required for tasks.


We need the time sheets for IT staff to show when activities are required for. Is there a way around this. If we run planning then all the activities planned dates will update.only project manager can do this and often causes a lot of work to resolve the issues a re-plan creates and sometimes can not work out why planned start dates are created.


Please see attached document with screen shots of this problem.
Attachments:

Please Connexion or Create an account to join the conversation.

More
04 Sep 2019 18:42 #2 by babynus
Timesheet does not show the planned dates, but the "more accurate" dates.
It means :
Real dates if set
Else Planned dates if set
Else Validated dated if set
Else requested dates (if set)

Planned end dates are displayed for instance on planning and on resource planning.

Babynus
Administrator of ProjeQtOr web site

Please Connexion or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.033 seconds

Paramétrages de cookies

×

Cookies fonctionnels

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Veuillez vous connecter pour voir vos activités!

Autres cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.