Resource not being assigned correctly

More
02 Oct 2019 12:22 #1 by jhoareau
Hello here,

I have a resource (me) assigned to a project.
This project contains activities on which this resource is assigned on.
The planning calculator does not calculate the duration correctly ; the activity is displayed inside planning per resource but with no duration for these activities.
When I look at the project planning, it does display the activity but for the day of today and with a duration of 1 day.
Screens below :
Affections of the resource "not working" :


Affectation of the differents resources on the project


Planning of the resource "not working"


Project planning


Example of an activity on which resource is affected on


Best regards,

Jordan
Attachments:

Please Connexion or Create an account to join the conversation.

More
14 Oct 2019 10:01 #2 by babynus
Hi,

Check capacity of the resource.
If capacity is zero, planning won't work.

Babynus
Administrator of ProjeQtOr web site

Please Connexion or Create an account to join the conversation.