ProjeQtOr free project management software - T&M project vs Income - ProjeQtOr

Prochaines Sessions

Les prochaines formations et démonstrations sont ouvertes, inscrivez-vous rapidement !

 

Démonstration de ProjeQtOr

(gratuit, sur inscription)
 

2 décembre 2025 (16h-17h30)

 
 

Planifiez avec ProjeQtOr

10 et 11 décembre 2025 (9h-12h30)

 
 

Administrez avec ProjeQtOr

16 et 17 décembre 2025 (9h-12h30)

 

 

 

T&M project vs Income

More
22 Oct 2017 14:59 #1 by ade
T&M project vs Income was created by ade
How can i manage the cost on a T&M project ?

I create projects, tasks, with affected users, those users declare their effort.

I want to declare all thoses efforts/ cost to my customer.

I want to make a snaphoot at the end of the week (sumup all costs/effort) in a order/bill to my customer.

How can i do that in efficient way ?

Thx for your help/

Please Connexion or Create an account to join the conversation.

More
22 Oct 2017 15:12 #2 by babynus
Replied by babynus on topic T&M project vs Income
Use "bill" item for billing mode "t&m"
Billing mode is defined on project type.
Project type is selected on project.
Then :
- you define activity price : selling daily price for activity type
- you add on bill 1 line per resource : select a priod and activity price
ProjeQtOr will retreive all "billable" work for resource on period for given activity type.

Babynus
Administrator of ProjeQtOr web site

Please Connexion or Create an account to join the conversation.

More
22 Oct 2017 16:05 - 22 Oct 2017 17:43 #3 by ade
Replied by ade on topic T&M project vs Income
This feature is available, great

let me decompose for my understanding :

I create a new Activities Type name "Selling Task"
I create a project with type set to "Time & Materials"
I create an activity on previous project with "Selling task" activity type
I declare real work allocation on the task (3 days with a cost of 300€ for ressource pierre), visible in the activity and in the project.
I declare an activity price on previous project with activity "selling task", price 50€.
I create a bill and enter 1 line per ressource for the period and activtity.

I excepted to have 300€ instead of 150€

Thx



-
Last edit: 22 Oct 2017 17:43 by ade.

Please Connexion or Create an account to join the conversation.

More
22 Oct 2017 18:51 #4 by babynus
Replied by babynus on topic T&M project vs Income
Cost is 300€ (I gues daily cost for resource is 100€ per day) but bill is 3xactivity price=150€ (activity price is 50€)
So you sell resource less than what they cost :(

Babynus
Administrator of ProjeQtOr web site
The following user(s) said Thank You: ade

Please Connexion or Create an account to join the conversation.

More
22 Oct 2017 21:36 - 22 Oct 2017 21:44 #5 by ade
Replied by ade on topic T&M project vs Income
Understood your answer and the way it is done :)

I have now to develop a way to automatically create all bill lines. B)

Entering manually the Sell cost of each profile may result in typing error and is not very effective => not acceptable for my business.

For my specific usage, I have to publish the bill weeky.
Last edit: 22 Oct 2017 21:44 by ade.

Please Connexion or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.048 seconds

Paramétrages de cookies

×

Cookies fonctionnels

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Veuillez vous connecter pour voir vos activités!

Autres cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.