ProjeQtOr free project management software - [SOLVED] How to change project planned end date - ProjeQtOr
 

[SOLVED] How to change project planned end date

More
25 Mar 2019 11:14 - 27 Mar 2019 14:03 #13 by clarezoe
I got another problem as shown in the screenshot that the second activity should be planned for April whole month with a fixed duration, however, it planed earlier and with shorter duration. I really don't get it. I have deleted all reported work and recalculated several times but nothing changes. Thanks for your patience and kind response!



And another example, you see the work in November was planed in October instead.

Attachments:
Last edit: 27 Mar 2019 14:03 by clarezoe.

Please Connexion or Create an account to join the conversation.

More
27 Mar 2019 08:28 #14 by babynus
Did you re-run planning calculation ?

Babynus
Administrator of ProjeQtOr web site

Please Connexion or Create an account to join the conversation.

More
27 Mar 2019 09:48 #15 by clarezoe

Please Connexion or Create an account to join the conversation.

More
27 Mar 2019 13:02 #16 by babynus
can you show detail of planned work (right click on task bar)

Babynus
Administrator of ProjeQtOr web site

Please Connexion or Create an account to join the conversation.

More
27 Mar 2019 13:09 #17 by clarezoe
Which task bar?

Please Connexion or Create an account to join the conversation.

More
27 Mar 2019 13:21 #18 by babynus
Gantt task bar of second actiivty (which is incorrectly planned)

Babynus
Administrator of ProjeQtOr web site

Please Connexion or Create an account to join the conversation.