ProjeQtOr free project management software - Repport / Planning / synthesis of availability - ProjeQtOr

Prochaines sessions de formation

Les prochaines formations et démonstrations sont ouvertes, inscrivez-vous rapidement !

 

Démonstration de ProjeQtOr

(gratuit, sur inscription)

Mardi 23 avril (10h30-12h)

Jeudi 16 mai (16h-17h30)

Jeudi 13 juin (10h30-12h)

 
 

Planifiez avec ProjeQtOr

3 et 4 avril (9h - 12h30)

 
 

Administrez avec ProjeQtOr

10 et 11 avril (9h - 12h30)

 

 

 
 

Repport / Planning / synthesis of availability

More
24 Avr 2019 15:20 #1 by pipobru
Hello,
Very thanks for your project, i use this since 8 years, on every new versions nice surprises with more and more amizing fitures !
On the last version (8.0.1) when i use rapport for check availability, new informations are display in ETP colon for ressources pool. My understand is the ETP capacity for the pool but my question is, why the capacity is negative for eatch month ? can you explain the algorith for calculate number of days availaible ?

Thanks
Attachments:

Please Connexion or Create an account to join the conversation.

More
24 Avr 2019 18:41 #2 by babynus
Availability for the pool is the (max capacity during the month) x (opened day) - (planned work).
It could be negative with real work that exceeds capacity of resource.
But it should not be negative when there is only planned work.
I found an issue in the calculation of (max capacity) for pools that may lead to capacity = 0, so negative value fits the planned work.
Fix will be included in next patch.

Babynus
Administrator of ProjeQtOr web site
The following user(s) said Thank You: pipobru

Please Connexion or Create an account to join the conversation.

More
26 Avr 2019 08:34 #3 by pipobru
thanks for your answer, and in ETP colum what is the signification of the label "max(1)
" ?

Please Connexion or Create an account to join the conversation.

More
26 Avr 2019 08:47 #4 by pipobru
I think i have found a probleme. With this last version, when i add new ressources in the pool the planification (duration) don't change. New ressources in pool not included in global capacity of pool in planning calculation. If i add directly new ressources on the task the planification is good.

Please Connexion or Create an account to join the conversation.

More
26 Avr 2019 09:00 #5 by babynus

thanks for your answer, and in ETP colum what is the signification of the label "max(1)

It is the max capacity of the resource for the period.
It can be variation in allocation for a pool, or variation in capacity for a resource.

Babynus
Administrator of ProjeQtOr web site

Please Connexion or Create an account to join the conversation.

More
26 Avr 2019 09:02 #6 by babynus

I think i have found a probleme. With this last version, when i add new ressources in the pool the planification (duration) don't change. New ressources in pool not included in global capacity of pool in planning calculation. If i add directly new ressources on the task the planification is good.

When you assign a Pool to an activity, you select the FTE assigned (number of resources from the pool that will work on the activity). Default is 1. So adding resources to the pool won't change unless you change this value.

Babynus
Administrator of ProjeQtOr web site

Please Connexion or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.059 seconds

Paramétrages de cookies

×

Cookies fonctionnels

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Veuillez vous connecter pour voir vos activités!

Autres cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.