Real cost doesn't reflect Real Work

More
28 Oct 2018 09:49 - 28 Oct 2018 09:58 #1 by cnguyen
Hi all,

I'm using Projeqtor 6.3.7

I've just done the following operations on a project.
3 resources on my project. Everyone has entered real work up to 31 october 2018.
On one of the resource, i have just entered a cost (C EUR) on the expert profile (This profile is the one my resource is assigned with for the projet / activity)
There was no other cost in the system for the resource.

On the project before entering the cost, real work was X days and real cost was 0 EUR
I saved the cost for the function of my resource on the project (Expert)
Back to the activity, the real cost is still 0 EUR.

Then I enter 1 day on the real wok allocation screen
Real work is now X+1
And real cost is now C EUR, which is the cost I have just allocated for the function.

Seems like real cost has not change for the already existing work.

Any idea ?
Thanks in advance.
Cyril
Last edit: 28 Oct 2018 09:58 by cnguyen.

Please Log in or Create an account to join the conversation.

More
28 Oct 2018 15:35 #2 by babynus

Seems like real cost has not change for the already existing work.

It should, I think current code does.

Any idea ?

Migrate to latest stable (V7.2.6).
(there were some fixes on the subject on V6.5)

NB : we won't analyse issues on older versions our of Support Service

Babynus
Administrator of ProjeQtOr web site
The following user(s) said Thank You: cnguyen

Please Log in or Create an account to join the conversation.

More
01 Nov 2018 14:59 #3 by cnguyen
Hi babynus,
Just upgraded to 7.2.6 and the issue remains the same.

Could you help ?

Thanks in advance
Best regards,
Cyril.

Please Log in or Create an account to join the conversation.

More
13 Nov 2018 08:35 #4 by cnguyen
Hi everyone,

@Babynus, we upgraded to 7.2.6 and real cost still doesn't reflect real work for already submitted "work".
We are a bit stuck with this and it's difficult to follow costs for these projects.

By the way : the upgrade to 7.2.6 has brought a lot of new functionalities for us that are really nice and helpful. Thanks for all the good work on Projeqtor :-)

Thanks in advance for your help.
Best regards
Cyril

Please Log in or Create an account to join the conversation.

More
13 Nov 2018 08:56 #5 by babynus

@Babynus, we upgraded to 7.2.6 and real cost still doesn't reflect real work for already submitted "work".
We are a bit stuck with this and it's difficult to follow costs for these projects.

You need to have some resource cost change to update cost from work.
Try and delete cost for resource then recreate it.

Babynus
Administrator of ProjeQtOr web site

Please Log in or Create an account to join the conversation.

More
13 Nov 2018 16:50 #6 by cnguyen
As there is some real work assigned with this function, I can't delete the cost

Error message I get when I want to delete the cost assigned to the function.
Impossible to delete this element because of existing dependent elements
- Assignment (10)

Please Log in or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.040 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.