Hello,
The load of a resource is not counted in the calculation and the different views (planning, global planning, reports, ...). Version 7.3.3.
See example in attachment.
It's exactly what I did but same problem.
I also validate the planning.
I haven't got any scheduled date in the task. Validate date (start and end) are inserted.
I guess you used "Administrative " for project type.
Administrative projects are not planned, there are used to store "out of duty" work (holidays, hillness, ...)
Just to be sure your project is calculated : change something on allocation of a task (left work for instance).
The icon of the project should change : get an orange center.
Then calculate planning : does icon of project is still with orange center or does it go back to normal white center ?
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.