ProjeQtOr free project management software - Error when calculating planning in view Planning (No data to display) - ProjeQtOr
 
 

Error when calculating planning in view Planning (No data to display)

More
15 Apr 2020 01:26 #1 by msassi
Hello,
Recently, I installed projeqtor V8.2.4
- I did my best to configurate projeqtor in interafce "global paramters". (Please see screenshot attached below)
- I created a custom workflow, project, some ressources
- I added some activities where ressources are assigned

Then I openned interface "Planning". Unlucky, I have following problems with planning :
- Not all planning are displayed. Planning is displayed only till current day. Only activities that were already filled by ressources into timesheet are displayed. (Please see screenshot attached below)
- 2 off days (Saturday and Synday) don't have grey colour. They are not shaded (Please see screenshot attached below)
- When right click into activity planned in current day, I have error "No data to display. Planning calculation required" (Please see screenshot attached below)

I need to get a complete planning.
Any help please.

Thank you in advance.
Attachments:

Please Log in or Create an account to join the conversation.

More
17 Apr 2020 09:18 #2 by babynus
Message in pop-op (at right click on bar) is clear : you need to calculate planning (use big gear button on planning screen)

Babynus
Administrator of ProjeQtOr web site

Please Log in or Create an account to join the conversation.

More
18 Apr 2020 01:34 - 18 Apr 2020 01:36 #3 by msassi
Hello,
If you mean button that I mentionned in attached screenshot, I answer that it doesn't resolve problem. (Please take look below to screenshot)
I used it since first time, and however planning is calculated I have always same problem.

Thank you in advance
Attachments:
Last edit: 18 Apr 2020 01:36 by msassi.

Please Log in or Create an account to join the conversation.

More
18 Apr 2020 19:25 #4 by babynus
When you click on this button, you get the list of projects that will be calculated.
Be sure to select your project and click OK.
Please post new screenshot afterward.

Babynus
Administrator of ProjeQtOr web site

Please Log in or Create an account to join the conversation.

More
18 Apr 2020 20:04 #5 by msassi
I did it but I have same error :( (Please see below screenshot)
I selected "All project", then I selected only my project and finally I selected all project I have but no way
Attachments:

Please Log in or Create an account to join the conversation.

More
19 Apr 2020 13:51 #6 by babynus
OK,
So your project or task is not planned.
Several possible reasons :
- you don't have right to calculate planning for this project
- project is administrative (lokk at project type)
- project has "fix planning" (look at value for checkbox)
- task has "fix planning" (look at value for checkbox)

Babynus
Administrator of ProjeQtOr web site

Please Log in or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.050 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.