Simply define a dedicated project (administrative project type has been set up for this).
Create tasks on the project as needed :
- holidays
- sickness
- training
- ...
Assign resources to dedicated tasks.
Then resource will just have to enter planed "off days" ar real wrok days on these tasks, and planning will not plan any other work these days.
(there is a planned evolution to avoid the assignment of resources : every resource should be able to input work on all Administrative projects tasks without needing to be assigned to the tasks)
can you please tell when this evolution to avoid the assignment of resources : every resource should be able to input work on all Administrative projects tasks without needing to be assigned to the tasks will be implemented?
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.