Hi,
Since few weeks, some activities status seems to be "blocked" :
1) when I create a new activity, after status "
accepted", it's impossible to move to status "
assigned"
=> a ressource is allocated, with same dates to the activity
=> in this status, I can allocate real work to the activity
2) when I want to stop an used activity (actually status "
in progress"), it's impossible to move to "
done".
=> I move the "rest to do" with 0 (no more work), and work percent is at 100% !!!
What are the constraints ? (if there are someone, of course...)
I think it was more easy before, with olders versions of ProjeQtOr.
Thanks for helping me...

Fred