Hello,
I've got a problem with planning. I have defined a main project and subprojects, assigned resources to the project and tasks with dates and rates compatible with the workload validated. I checked also that globally no resource is assigned at more than 100% on all projects.
However, when I try to calculate planning for the project (the goal is to get the workload assigned so each resource gets its assignation and manager can see resource availability in the reports), the tasks where resources are assigned work cannot be planned with an error.
Here is an example of error found :
In this example, the green tasks have resources in assignation with no workload assigned, tasks in purple have at least 1 resource with workload assigned. In this case, all tasks with resources with workload assigned are planned at a date in the future, and only planned on 1 day while all tasks should be running on multiple days.
No problem is found until at least 1 resource gets assigned work in a task. But without that assignation, there is no possibility to plan anything correctly.
Do you have any clue on how to solve this problem ? I may have done something wrong but I have made tests on a test server without this kind of problem before, so I'm a little bit lost.
Thanks a lot !