Hello,
I have someone who work on a project "P1" at 100%.
This person have a training for 1.5 days during this project "P1".
Training activity have a higher priority than tasks on P1.
My problem is that I have a message when trying to calculate the planning for the "training" project, saying that activity can't be scheduled.
Indeed this person is planned to work on a tasks on P1 but what I don't understand is that this tasks can start before "training" activity and end after. It seems that planning calculation tool can not interrupt a task for some day to allow another one to be inserted ???
What have I done wrong ?
Check affectation of resource "Michel" ro project "Formation".
Maybe start or end date of affectation (I would bet on end date before 06/06) forbids planning at the expected date.
I made tests on affectations, ie remove end date for "formation" project (no start or end date on other porject), and now the task is planned but it's not what I want to plan as "formation" is at fixed date (06/07 to 07/07), I want that other task on project "etude carte" start before this "formation" and remaining work end after "fromation".
See below "monthly planning for michel " before test:
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.