10 Jun 2016 11:20 #7 by mvern
Hi Babynus,
The priority between both project was already different (400 for "formation" and 500 for "etude") but with no effect ...
I have modified a lot of things on different projects and now I don't see the pb anymore, could it be because I was only recalculating these 2 projects and now I have recalculate planning for all projects ?
For your recommandation, I'm not sure to understand it? you mean that I have to fill in "work done" in advance ?

Please Log in or Create an account to join the conversation.

More
12 Jun 2016 12:26 #8 by babynus
HI,
I still cannot reproduce your use case.
Could you try and reproduce on the Demo ?

you mean that I have to fill in "work done" in advance ?

Yes, you enter real work for this "fixed" task, and you're sure it is correct.

Babynus
Administrator of ProjeQtOr web site

Please Log in or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.032 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.