Hello,
I have a problem of understanding on the use of milestones.
I want an activity begins after milestone (milestone = hardware delivery, activity = hardware configuration).
If I set a milestone and a successor activity, there is no problem in the schedule.
After, if I assign a resource to the activity, it starts before the milestone (the current day). The planning activity is configured as "as soon as possible".
Strange, all seems correct, and I can confirm that correct result is exactly what you expect ... and what I get.
What is the project type of your projects ? (Configuration PC and its parent)
Can you try and create dependency from milstone to sub-project "Configuration PC" ? What is the result ?
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.