Congratulations for this version! It responds very well to the demands of all users!
My remarks
- For "real work allocation" : To have a choice between entering hours and days. The project still manages day (duration of one day time will be defined by admin) ?
- Add the resource list in the schedule (Gant view). This will more easily see their availability in the planning.
- All cells filled automatically in gray. Today only the text is grayed and if there is no text it is not easy to see automatic cells.
- Always my request => To copy a set of activities and milestone (parent activity)
Thanks for your good job !
For "real work allocation" : To have a choice between entering hours and days. The project still manages day (duration of one day time will be defined by admin) ?
Yes, duration in hours of one day time is defined in new Global Parameter Screen (have a look at user Manual, fully updated.
Add the resource list in the schedule (Gant view). This will more easily see their availability in the planning.
Good Idea. Graphically, how would you expect such a view ? Display the list facing gantt bars (like on MS-Project defaut presentation) ? on a new data column ? else ?
All cells filled automatically in gray. Today only the text is grayed and if there is no text it is not easy to see automatic cells.
Why not. To be studied (should not dispkay fields i ngrey text on grey fiels : visibility should nbot be good.
Always my request => To copy a set of activities and milestone (parent activity)
For "real work allocation" : I have project follow up in hours and other days. For simplicity I propose that each (ressources) define how can pointing a week. Either in hours or in days. The project is following him that day.
babynus wrote: Set possibility for each resource to define unit for real work imputation : why not, but this is source for lot of rounding issue.
Ok
babynus wrote: For the resource planned work : some reports exist with these view. Is it what you expect on Gantt view ?
Yes but when I plan the activities, I use to 'follow-up/planning' view => I need to understand why it shifts activities => Having the resources to occupation will help in planning.
Is too long to go to view report and return to 'follow-up/planning' view
babynus wrote: In Gannt view : select fields to display : yes, it's planned. Change order : not planned (not so easy and other major evolution are waiting...).
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.