Thanks ! I'm in progress due to your help !
Well graded for the function of resource on the assignment.
I edited my previous post, because i have done a bad copy/paste.
if i understand, many possibilities concerning assigment of a/many resource(s) on a task :
- 1) only one resource assigned
- 2) 2 resources with mode planning "as soon as possible" : in this case, it's possible that 2 resources are planned to work in the same time on this task
- 3) 2 resources with mode planning "work together" : in this case, scheduling calculation planned days work whose 2 resources have availability days.
Q it's ok for you ?
i think that for 1.5,1.6,1.7 tasks, we were in the second case. However Maxime planned to work 23,24,25 august while he was in days off.
And i don't know why. that's why i try to test again with 2 resources on a task.
Following some modifications, i modified again the 1.5 task like that :
- guillaume (developer) : assigned with 1 day
- maxime (developer) : assigned with 2 day
Now, planning seems to be ok.
Q Do you know the reason ?
Thanks a lot.