Rate = 0% means resource cannot work (or at least won't be planned) on the task.i didn't fill the field "rate (%)" for the resource "Guillaume".
Right click on bar show, day by day, the exact planing for resources. It helps understand what was calculated.right click on each bar permits to validate than the scheduling calculation ran correctly, isn't it ?
How did you enter "off days" for him in projeqtor ?The planning planned for Maxime, to work on 1.5 task the 23,24,25 August, while he is on days off .
Of course not. Validation of planning is juist copy of planned dates to validated dates (some kind of initial baseline)I wonder if the click of the "validate planning" button explains that
Not possible.1) constraint to skip than 2 resources on the same time work on an task ?
No, ProjeQtOr won't decide it for you. It's your Project Leader job to decide how will work.I wonder if i can assign 2 resources on a task, and according to availability of resources, scheduling c
Please Log in or Create an account to join the conversation.
babynus wrote:
Rate = 0% means resource cannot work (or at least won't be planned) on the task.i didn't fill the field "rate (%)" for the resource "Guillaume".
ok. i didn't set 0 for the field "rate" but i understand here, that it means "empty" value = 0
Right click on bar show, day by day, the exact planing for resources. It helps understand what was calculated.right click on each bar permits to validate than the scheduling calculation ran correctly, isn't it ?
ok. it's very interesting to see that (good idea !)
How did you enter "off days" for him in projeqtor ?The planning planned for Maxime, to work on 1.5 task the 23,24,25 August, while he is on days off .
i input in the menu "Follow-up > Real work allocation" (shown below)
I wonder if the click of the "validate planning" button explains that
Of course not. Validation of planning is juist copy of planned dates to validated dates (some kind of initial baseline)
Well-graded
Not possible.1) constraint to skip than 2 resources on the same time work on an task ?
ok. Then, the solution is going to assign only one resource.
No, ProjeQtOr won't decide it for you. It's your Project Leader job to decide how will work.I wonder if i can assign 2 resources on a task, and according to availability of resources, scheduling c
Remember that even if softwares like ProjeQtOr are call Project Management Tools, they are only project organisation tool. The project management is your job, ot's not done by the tool.
Please Log in or Create an account to join the conversation.
YesIt's the good method ?
Please Log in or Create an account to join the conversation.
Please Log in or Create an account to join the conversation.
As you entered some real work for him for his whole capacity on these days, the only possibility is that planning calculation was not executed for the project.projeqtor80 wrote: perfect.
Do you know the reason whose explains that the scheduling calculation planned for Maxime the 23,24,25 August ?
Please Log in or Create an account to join the conversation.
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.