I would like to know if it's possible than gantt after "real work allocation" for exemple 0.5 day on 2 days left work , the gantt keeps the bar visible for 2 days.
Because currently this leads to a bad interpretation of the gantt by some people (see sample in file attached ).
I create only an activity on 2 days by example
After , i allocated a ressource for 2 days
After in the real work allocation , i have imputed 0.5 day and save (with the icon diskette)
After a check, i see than : start date and end date (in PLANNED) are complete on the date imputation, maybe it's anormal ....
hi
Could you check, please, the value of FTE of this resource when you allocate it to this project. Is it 2 on this box ? (and not a value beetween 0,1 and 1 as expected)
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.