In Activity - New Task if I try to add resource using "+" in assignment area it will not populate the list of resources and manual typing producing always "The value entered is not valid" message.
I can add resource using "responsible" field (still no population for drop down box but search button is producing resource list) but only ONE resource. Looking like there is no way to add second resource. So, what I am doing wrong?
Sorry - found the reason for the problem - it is in affectations which done wrong. Can you please explain how to do affectations for multiple projects when people involved kind of time-to-time in different projects but on 100%?
Regards
Affectation definition includes affectation rate to the project.
For instance, if a resource works evenly on 5 project, oyu can define affectation rate at 20% on each.
This way, planning process will plan work for resource 1 day per project each week.
Another way is to assign to tasks at a 20% rate. Then resource will be planned only 20% on each project each day.
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.