Hi
I tried with version 7.2.7 but it's the same thing
If left work is not set to 0 then projeqtor is unable to calculate planning.
Look at this planning : activity "specification" is well displayed on Gantt but left work is set with 0.
Now I decide to increase left work to 30 and I save. As you can see, activity progress changes on Gantt and it's OK.
Now I launch planning calculation and activity specification "disappear" (in fact, just 1 day is displayed on gantt and planned duration is only 1 day)
Explain me if it's not an issue ...
Regards
Attachments:
Last edit: 09 Nov 2018 18:54 by apad. Reason: Add pictures
What can explain this is capacity of resource : capacity is Full Time Equivalent. Thids means that normal resources have capacity of 1 (hability to work 1 day poer day).
Possibly you changed capacity to more thant 30.
For instance if you changed capacity to 100, it means resource can work 100 days per day, so can finish 30 day task in 1 day.
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.