Possibly it is because you try to calculate a planning "in the past".Whatever I can enter for left work (except 0 which means that task is done) I got the same result.
Real work is not "calculated". It is entered by resources on Timesheet screen.I can't enter value for real work because it is calculated.
Calculation takes into account "contraints" (assigned work, availability of resources, planning mode, dependencies). It does not take into account "validated dates".these are just for control of expected planning (baseline)Is there à way to clear calculation result ? It's look like calculation ignore what I can enter.
Please Log in or Create an account to join the conversation.
Tried but nothing changedTry and change planning calculation start date in the pop-up that triggers planning calculation.
OK real work is entered on Timesheet screen but agregated (calculated) in activity screen.Real work is not "calculated". It is entered by resources on Timesheet screen.
In my example, task "Analyse du besoin" is "planned" between 01/08/2018 and 15/11/2018.Calculation takes into account "contraints" (assigned work, availability of resources, planning mode, dependencies).
Please Log in or Create an account to join the conversation.
Please Log in or Create an account to join the conversation.
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.