[SOLVED] Resource affectation

More
17 Nov 2018 09:41 #7 by apad
Replied by apad on topic Resource affectation

Yes.
But I thing you missunderstand how to plan a projets.

In projeqtor, it's true.

You just have to change "assignment rate", on each activity.

You said before that my allocations were complex. It won't be better if I do the job for each task...

And last (but not least), as you did, your allocation rates will have absolutely no effect as you did not define assigned work on activities...

I know that, it was just à light sample on your demo database.
Please remind my topic "9528-planning-calculation", when assigned work is set, Projeqtor is unable to calculate the planning...

Please read user manual about planning rules ;)

I read it but rules are not clear :( or I did not find the good pages...
Regards

Please Log in or Create an account to join the conversation.

More
18 Nov 2018 10:30 - 18 Nov 2018 10:31 #8 by babynus
Replied by babynus on topic Resource affectation

You said before that my allocations were complex. It won't be better if I do the job for each task...

No, it will be much more easy with assignments to activities.
And it will be dynamic : just extend duration of activity will take into account changes for availability; you won't have to update allocation to project

I know that, it was just à light sample on your demo database.
Please remind my topic "9528-planning-calculation", when assigned work is set, Projeqtor is unable to calculate the planning...

I think you mostly use planning mode "don't start before validated start date". But this mode will always plan "as soon as possible" after start date.
Possible you need "fix duration" planning mode (and then have dependency if you want to start after given date) or "regular between dates"

ProjeQtOr is not a tool to "draw" a planning, but to calculate the best planning (shortest duration) depending on contraints cyou define.

Babynus
Administrator of ProjeQtOr web site
Last edit: 18 Nov 2018 10:31 by babynus.

Please Log in or Create an account to join the conversation.

More
18 Nov 2018 16:06 #9 by apad
Replied by apad on topic Resource affectation
Hi

ProjeQtOr is not a tool to "draw" a planning

I know that and it's why I use it ;)

If I use only assignments to activities instead of affectations to project, I loose view on resource availability.
It is very interesting to know if a ressource is "used" more than 100% on a period.
I tried to use both affectations and assignments but Projeqtor "failed" to plan activities.
Anyway, thank you for time you spent to answer my questions.
Soon, I will have a training to Projeqtor planification. It'll be easier.

Regards

Please Log in or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.043 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.