Resetting Real Dates

More
26 Jun 2015 15:50 #1 by jstraight-griggs
Hi, I'm looking for a way to edit real dates, is this possible for the scenario below?

I setup a project template and then copied it to new project. During the copy it took what appeared to be my fixed duration tasks and set a real start date using today's date, even though there were no hours charged and in these specific cases not even resource assignments. This of course created out of sequence progress, etc.
I ended up deleting and re-adding the fixed duration tasks, however, now even summary bars still have the real dates and of course deleting/reading those is a much larger job. So I'm looking to remove the real dates from the summary tasks.
Also, is this a bug and if yes, what work around should I use? Do not use fixed duration?

Thank you
Judy
The topic has been locked.
More
29 Jun 2015 09:28 #2 by babynus
Replied by babynus on topic Resetting Real Dates

I'm looking for a way to edit real dates

Real dates only come from "real" situation.

During the copy it took what appeared to be my fixed duration tasks and set a real start date using today's date

It is possible if status of activity is "done". Otherwise, it should be an issue.
I tried to reproduce, but is status of template is not done, real dates of copied items are not set.
If you reproduce with not done status, please post more details (print screen, detail of activities, example on demo...)

Babynus
Administrator of ProjeQtOr web site
The topic has been locked.
More
02 Jul 2015 14:33 #3 by jstraight-griggs
Hi, I've attached a document that shows the template and the resulting copied project. Please let me know if you need additional information or have difficulty opening. Thank you

File Attachment:

File Name: ResettingR...ots.docx
File Size:1,166 KB
Attachments:
The topic has been locked.
More
03 Jul 2015 16:25 #4 by babynus
Replied by babynus on topic Resetting Real Dates
The difference between template and copied is status : template has "proposed" status (means not stated)

Activities have "Active" status (means started).
So, activities with not planned work but started status automatically have real start date.

Babynus
Administrator of ProjeQtOr web site
The topic has been locked.
More
06 Jul 2015 22:31 #5 by jstraight-griggs
So I think you are saying the system marked it started because I changed the status to Active. Do summary and fixed duration tasks (zero work) need to be changed to active at any point during the project or can they always stay in a copied state?
The topic has been locked.
More
07 Jul 2015 11:01 #6 by babynus
Replied by babynus on topic Resetting Real Dates
Copies state is very temporary status.
Is is used mainly to avoid alerts, emails and else that could be generated before the copied item is updates (copy is never exactly the same as original).
Best is to move to some 'in progress' status.

Babynus
Administrator of ProjeQtOr web site
The topic has been locked.
Moderators: babynusprotion
Time to create page: 0.044 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.