We need your help because we encountered a problem with planification.
On a project that use predecessor chaining rule, we have many task that are planified to start before predecessor ending.
All task concerned are test session plannified on planningMode : as Soon as possible (9)
there is only one predecessor by task (testsession)
Planning of both task
Detail of predecessor test session (with end date on red)
Detail on successor test session with contraint date
Database View of Planning Element
Do you have any ideas to explain this case, a solution so that this constraint is respected whatever the other constraints that apply
Is there some real work entered into the succesor ?
Is the sucessor is planified with a special mode as regular beetween to dates or planified intervention ?
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.