ProjeQtOr free project management software - Planification problem - Predecessor End to Start not respected - Page 3 - ProjeQtOr
 
 

Planification problem - Predecessor End to Start not respected

More
23 Sep 2020 09:34 #13 by QUANTAMEDICAL
I found origin of problem :
there is an E-E predecessor dependency on parent (Task 3014 have parent "Developpement" 3639)
3639 have predecessor End to End with task already ended "Validation du cahier des charges" (3643) and "Création environnements développement & validation" (3855)
In principle, the development task (3639) cannot be completed until the 2 predecessor tasks are completed.

but there seems to be an interpretation problem which causes the start date to be the end date of the E-E task and the E-S constraint of the 2567 task is not taken into account
When i delete both E-E predecessor of developpement (3639) , start date of 3014 taken account of 2567 E-S constraint


Attachments:
The topic has been locked.
Moderators: babynusprotion
Time to create page: 0.049 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.