Hi
In Activity under Progress tab ->Assignment: If real work hours are already available & Assigned hours are being added later then left work is not being updated auto!
Behavior is normal : You had 0 assigned, 0 left, and you entered 12 for real. OK
After that, you enter 24 assigned, so it means you add 24 to existing, so left is 24. You'll have to change it manually if it's not whan you expect.
Because left in not alwayd Assigned - Real.
Imagine you have Assigned = 10, entre Real = 7, left is automatically calculated to 3, but resource can change Left to 5, so reassessed is now 12 (assigned is underestimated) This happens all the time.
Then if you add extra work and set Assigned=15, then left will be set to 10 (you add 5 to assigned, so Left is increased of 5). We don't mind about existing real.
This works the same way is assigned is zero... if you Add some assigned work, left will be added the same added value, whatever existing real work.
Once again, if it's not what you expect (for instance you want to fix some incorrectly assigned work) you can very easily change the left work.
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.