One question more, my team is working on "real projects" and "run projects" (activities from day to day), so if I want to plan some projects and my "run projects", what is your recommendation to plan it on ProjeQtOr? because "run projects" is a task that is cyclic but I don't know how to add it on ProjeQtOr (which planning uses ... etc)
PD: I know the % that my team is free for "real projects" and the other % to do only "run projects".
One question more, my team is working on "real projects" and "run projects" (activities from day to day), so if I want to plan some projects and my "run projects", what is your recommendation to plan it on ProjeQtOr? because "run projects" is a task that is cyclic but I don't know how to add it on ProjeQtOr (which planning uses ... etc)
Use the "regular between dates" planning mode. It's done for this.
You define start and end dates (for instance 01/01 => 31/12) and assign resource with expected work for the period. Planning will reserve work, reguliarly.
You can also opt for "in half days" or "in full days" if you don't work to book 0,1 day par day.
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.