ProjeQtOr free project management software - [SOLVED] Teams are not working at fully time on project - Page 2 - ProjeQtOr
 

[SOLVED] Teams are not working at fully time on project

More
19 Oct 2015 16:14 #7 by babynus
Because no resource if affected to the project : you did not define the project team.
First affect resources to the project.

Babynus
Administrator of ProjeQtOr web site

Please Log in or Create an account to join the conversation.

More
19 Oct 2015 16:35 #8 by El Wallos
Ah ok, for example, I affect 100% on the project screen and if I affect on the task 40%, so the ressource will work 0.4 day every day of the week, is it right?

Je mets la traduction en Francais pour éviter les quiproquos avec l'anglais:

Si j'alloue 100% de la ressource au projet et 40% sur la partie de la tache (activité), alors la ressource travaillera 0.4 jour sur cette tache tous les jpours de la semaine.

If I mix, I affect 80% on the project screen and if I affect on the task 40%, so the ressource will work 0.4 day during 4 days every week.

Si je mélange les deux, et j'alloue 80% de la ressource au projet et 40% sur la partie de la tache (activité), alors la ressource travaillera 0.4 jour sur cette tache pendant 4 jours de la semaine.

Dis moi si j'ai bien compris..

Please Log in or Create an account to join the conversation.

More
19 Oct 2015 16:52 #9 by babynus

Ah ok, for example, I affect 100% on the project screen and if I affect on the task 40%, so the ressource will work 0.4 day every day of the week, is it right?

If I mix, I affect 80% on the project screen and if I affect on the task 40%, so the ressource will work 0.4 day during 4 days every week.

No.
Resource will work 0,4 days each day, with a maximum of 4 days of work per week on the project. In your case, the affectation rate has no effect as 0,4 x 5 = 2days, which is less than limit of 4 days. In your case, affectation rate to project will have effects only if resource is assigned to other tasks on same project.

Babynus
Administrator of ProjeQtOr web site

Please Log in or Create an account to join the conversation.

More
19 Oct 2015 17:10 #10 by El Wallos
Sorry but I don't understand. Your answer was for which ratio?

Could you explain me again with this number?

Project Screen: 100% Activity Screen: 40% ----> ressource will work ...

Project Screen: 80% Activity Screen: 40% ----> ressource will work ...


because I don't understand what is the impact of the Project Screen Ratio.

Please Log in or Create an account to join the conversation.

More
19 Oct 2015 17:40 #11 by babynus
Hope it will be more clear with a small tables with all possibilities for project affectation rate combined with activitie assignment rate for values 100%, 80% and 40%

Babynus
Administrator of ProjeQtOr web site
Attachments:
The following user(s) said Thank You: fmoyer, El Wallos

Please Log in or Create an account to join the conversation.

More
20 Oct 2015 09:25 #12 by El Wallos
Thanks a lot Babynus, sometimes, one image explains better than 1000 words B)
The following user(s) said Thank You: fmoyer

Please Log in or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.049 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.