How can I check if one ressource is assigned on two different tasks at the same time (100%)?
For example, RR is assigned on two projects the same day (20 Oct 2015) and no alert is displayed, so what is the way to detecte it?
There is no alert because it is not an issue : resource can be affected on same period on several projects, and total affectation can be more than 100%.
You can see affectation summary on resource screen.
How to detect overload on the same ressource?
There is not overload of resource in ProjeQtOr planning !!!
If resource is planned on 2 tasks that should come same day then one of the two is extended on following days (witch is delayed depends on priority of tasks, have a look at priority in planning calculation in the user manual).
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.