Submit :
=> Only the concerned resource can do it
=> it indicates to the Project Leader that work input is complete
=> resource can still un-submit work to make some changes
=> Project Leader can also un-submit to indicate he does not validate input (then he should add comment on top of screen)
Validate :
=> Only Project Leader can do this
=> it indicates that the Project Leader validates the input of the resource
=> the resource cannot un-sumit any more and so cannot change work input for this week
=> Only Project Leader can un-validate in order to un-submit from resource and then change work input
If I want to reevaluate a task, what's happen if my plan work was 10d and the Real Work Allocation is 10 d, how can I reevaluate the work? (because if the planned work is egual to the plan work, the task should be terminated)
And why I can't closed an activity with left work (in my understanding, this case happens when a ressource has finished his activity before the plan work)?
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.