Hello
I have an activity with 5 days workload.
I use planning mode "regular in days". I expect to see only 1 in the planning per day.
Note : the resource has a FTE = 1
But 0.1 work appear in the planning, it seems that the last days is splitted in pieces :
There is no other part-day activity on the same date in the planning that would explain that this day must be splitted
This also happens when using "regular in half days" or "regular in quarter days".
I can see that on several of my projects, and always have the issue on the last planned day that is splitted in pieces.
What can be the cause of this behaviour ? Is there a workaround ?
But instead the last day is splitted in 0.1 or 0.2 workloads like in my screenshot on previous post.
It does not happen all the time. But on some projects I have this behavior and do not understand why.
Is there something I can check ? Something that would explain that ?
For the regular planning mode, you must set the validated duration (start and end dates).
Second, you define the planned work (assigned work).
In your case, you should use the planning mode "Regular in full days".
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.