23 Aug 2017 23:13 #1 by projeqtor80
Hello,

congratulations for this application !

i try to understand as more as possible how to run this application.

Below, many projects with tasks.
2 resources (Maxime,Guillaume) work on this tasks.
task 1.5 -> on the bottom of this picture, 2 days for Maxime, 1 day for Guillaume.



Why the planning defined the 1.5 task on this period ?
Maxime, Guillaume are days off 23,24,25 August.






Why the 2.1 task doesn't represent by a bar on this picture below ?



Thanks a lot.
Attachments:

Please Log in or Create an account to join the conversation.

More
23 Aug 2017 23:30 #2 by babynus

Why the planning defined the 1.5 task on this period ?

1) Check planning mode : by default it is as soon as possible...
2) Right click on task bar : you'll have detail of planned work
3) Use reports in catagory "planning" to analyse planned work

Why the 2.1 task doesn't represent by a bar on this picture below ?

Please show detail of task with all details of "progress" section.

Babynus
Administrator of ProjeQtOr web site

Please Log in or Create an account to join the conversation.

More
23 Aug 2017 23:51 - 24 Aug 2017 00:07 #3 by projeqtor80
Thanks for yours responses.

1) this 1.5 task seems to be "as soon as possible" (shown on the picture)
the "congés & RTT" project defined on "Administrative project".

2) i tried the right click on the bar of 1.5 task : i have had a message (shown on this picture)



3) i'm trying to see reports now

4)
Attachments:
Last edit: 24 Aug 2017 00:07 by projeqtor80.

Please Log in or Create an account to join the conversation.

More
24 Aug 2017 00:21 #4 by babynus
It seems you just did not run planning calculation : use button with gears

Babynus
Administrator of ProjeQtOr web site

Please Log in or Create an account to join the conversation.

More
24 Aug 2017 00:29 - 24 Aug 2017 00:32 #5 by projeqtor80
i had clicked on the button "calculate activities planning" and i havec this message.
But i don't get this message on all bars.
For example, not for 1.1 1.2 1.3 tasks. i get more details information.

with a report "monthly project activity resource", i don't get all tasks of projects :



i'm seeing 1.1 1.2 1.3 tasks.

Do i click on validate planning ? I don't know consequences ...
Attachments:
Last edit: 24 Aug 2017 00:32 by projeqtor80.

Please Log in or Create an account to join the conversation.

More
24 Aug 2017 08:43 #6 by babynus
Possibly you did not calculate all projects, but only current one ;)

Babynus
Administrator of ProjeQtOr web site

Please Log in or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.144 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.