The question for me is: why the capacity of pool is used only on end of month ? I have tested to force the start date on eatch resource of the pool, without impact
Because the pool is made from resources.
And the resources already work on other tasks.
Sum of work planned for all resources and for the pool cannot be more than sum of capacity of the resources.
The pool is not an extra resource.
Thanks but the last line "total" for the pool show never the full ETP capacity (3 ETP) exept the end of mounth (29/04) The calculation split my activity "TAT TCO MRO (Weekly)" with 1,84 total VS 3 days ETP maximum available..
I have create an picture for explain:
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.