24 Jan 2016 12:08 #1 by hawkeye
PERT-Termination was created by hawkeye
Hello,

is it possible to include the units "minute" and "second" in the JSGant PERT-Termination. :woohoo:

Thank you :)

Please Log in or Create an account to join the conversation.

More
24 Jan 2016 14:57 #2 by babynus
Replied by babynus on topic PERT-Termination
Soirry, I don't understand tyhe request.

There is no PERT in ProjeQtOr.
I don't understand what is "JSGant PERT-Termination"

Could you please explain tour request ?

Babynus
Administrator of ProjeQtOr web site

Please Log in or Create an account to join the conversation.

More
25 Jan 2016 13:25 #3 by hawkeye
In the actual implementation of ProjeQtOr it is possible to do the PERT-Scheduling,Gant-Scheduling (or Termination en.wikipedia.org/wiki/Program_evaluation_and_review_technique) by entering the relevant dates in the form of dd/mm/yyyy.
The question is if it possible to enter the to be calculated start-/end-dates of the activities in a higher precision like dd/mm/yyyy hh:mm or even dd/mm/yyyy hh:mm:ss and then do the Gant- or PERT-Scheduling of the start-/end-dates of the projectactivities where the project system ProjeQtOr would schedule/terminate all activities in the entered precision.
In the best case that would mean that all project- and activitiesdates as well as all durations within a project could be scheduled accurate to the second. :woohoo:

Thank you. :)

Please Log in or Create an account to join the conversation.

More
25 Jan 2016 19:00 #4 by babynus
First, there is not PERT in ProjeQtOr, only Gantt.

Second, when you plan in ProjeQtOr, you don't enter start/end dates : this would be just to draw a Gantt. I ProjeQtOr, you define constarint for the tasks : assigned resource, work assigned, dependencies, priorities, rates, ... and ProjeQtOr calculates planning taking into account all the constraints, on all the projects.

There is abolutely NO interest to display start/end with Seconds acuracy...We are dealing with Project Management, not launching a rocket.
Internally, ProjeQtOr manages start/end with minutes accuracy, but it's not dislayed.

Babynus
Administrator of ProjeQtOr web site

Please Log in or Create an account to join the conversation.

More
26 Jan 2016 13:17 #5 by hawkeye
Replied by hawkeye on topic Detailed scheduling
More detailed planning would be also applicable in event planning like concerts. As long as no one needs this it is of course makes no sense.

Thank you. :)

Please Log in or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.040 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.