Change the unit hours by day, then change the number of hours, then come back from day to hours. The Number of hours will be kept. it is a trick. It is not recommended to change the duration of work by day. Indeed, from now with this new unit, some workload will be missing on the past, just to keep in mind reading reports and so on.
In addition to Alainforma's remark, you should not change hours per day parameter when some real work exist.
Keep in mind that Projeqtor stores work in days. So enter and display in hours is a conversion.
You have 5 hours per day.
If you have a user who entered 5 hours for a day in timesheet, projeqtor stored value 1 (1 day)
Now if you change hours per day to 10, same user reading his timesheet now sees 10 although he entered 5...
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.