I need to have the time assigned for each of my ressources on each activity and export this to a spreadsheet
In the report I can only have reports with the time assigend for a ressource on a project, but NOT on an activity
The "ressources planning" screen shows exactly what I want but it is not possible to export it to a spreadsheet format (print and pdf are the only options)
Is there a way to get what I need from projeqtor ?
too bad
I think such a report would be useful (there are reports on the time assigned on projects but not on activities)
or at least the possibility to export to spreadsheet the "ressource planning" screen
do you know if it is on the product roadmap ? Or maybe i should create topic in the "proposed evolutions" part of this forum ?
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.