I'm a new user and I'm encountering an issue with my project's planned days. Here are the details:
- I set my project start date to 1st July 2024 and end date to 1st July 2025, resulting in a validated duration of 262 days.
- I created a resource and added a couple of activities. These activities are assigned to the project, but I did not specify start/end dates for them.
- For some reason, the "planned" days for the project adjusted to 92, which is significantly less than the validated days.
I’ve reviewed all settings and configurations multiple times but can't identify the cause of this adjustment. Could anyone provide insight into what might be causing this issue or suggest any steps to resolve it?
IT is just because it is not the duration of the project that will determine the duration of tasks.
It is reversed.
Duration of tasks will determine the duration of the project.
PorjeQtOr is not just a drwing tool.
It calculates a realistic capacity planning depending on resources capacity.
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.