First, congratulations for your work : your software is very good and very useful.
I have a question : how can I assign a new resource to a projet at a fixed date? (after the project has begun). For example : my project start the 15/01 but the resource is only available the 01/02.
It is not possible yet.
This evolution is planned : Ticket #164.
.. but not considered urgent
You must manage differently.
For instance :
- put a contraint to firt activity of this recource
- manage all your projects with Project'Or RIA : this way the availability of all resources will fit reality
- define some specific task (maybe on administrative projet) such as "Other Projects", and enter some real work for the resource for the unavailability period.
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.